Before renovation - Sacramento property
Before
Sacramento B2B Project View 1
Sacramento B2B Project View 2
Sacramento B2B Project View 3
Sacramento B2B Project View 4
Sacramento B2B Project View 5
After

2 ADUs

Folsom, CA

Project timeline

11 months

Onsite timeline

5 months

Budget variance

1%

Project details

Villa added two detached ADUs to this 428-unit REIT-owned property in Folsom, CA, delivering three-bedroom, two-bath layouts with premium finishes and private entrances. The Villa team designed the optimally sized units to capitalize on unused land on the multifamily property. The project was completed in 11 months with just five months onsite and within 1% budget variance. Built offsite and installed on permanent foundations, the units quickly leased at a premium over comparable apartments on the property.

Villa partners with multifamily operators to seamlessly add high-ROI units to their properties, managing every step from site planning and permits to construction, installation, and warranty support. To learn more, click here.